Goddard Residence
Friday, November 15, 2013
Day # 61 - More Travertine!!
Fire Pit Area!
Pathway to the Ramada!
Back towards the house!
Day # 60 - 2 months...wow!!! Leave you in suspense :) no photos for Day 60
Wednesday, November 13, 2013
Day # 59 - Travertine going down, water features getting wrapped up, etc.
Spa water feature :)
Waterslide :)
:)
Planters done with stone
Travertine coming along!
Looking good!
Tuesday, November 12, 2013
Day # 58 - Stone going up on the Ramada
One planter almost done
:)
From a distance
Roof tile done!
One step closer to completion!
Monday, November 11, 2013
Day # 57 - Travertine is being placed and water features getting finished up!
Wow!!! Coping being cut
Steps into the Ramada
Water slide almost complete
View from atop the slide!
Day # 55 & 56 - It's the weekend!!! No breaks around here!
Lay pipes and back-filling!
Day # 54 - Not much production....just clean up!
Day # 53 - One planter complete, roof tile on and water features continue
One planter built!
Roof tile is on!
Water feature continues!
Water feature continues!
Wednesday, November 6, 2013
Day # 52 - Back to work on the water features. Roof tile starts too!
Water features in back in progress!
Now you can tell what it is going to look like!
Behind the spa
These guys were fun to watch
Really coming together
Tile will all be placed tomorrow
Tuesday, November 5, 2013
Day # 51 - Gas line being placed and concrete counter tops
Gas line is going in!
Almost there!
That's some heavy counter tops
OK, we almost have it level :)
Concrete counter top is in!
All done!!!
Day #50 - Final Framing for inspection tomorrow
All the framing is complete and ready for inspection, then roofing!
Sunday, November 3, 2013
Day # 49 - Trenching for the gas line, etc....
Patio extension is all framed!
Trenching for the gas line!
Day #47 & 48 - Patio extension continues
Patio Extension continues!! :)