Goddard Residence
Thursday, October 31, 2013
Day # 46 - Trusses in place, beam set for patio extension and BBQ island started
For the fridge and electronics
For the BBQ grill :)
The trusses are up!
:)
It's really coming together!!!
Day # 45 - Slow day visually......bolting plates to the trusses
Tuesday, October 29, 2013
Day # 44 - Trusses are set temporarily, stairs and cabinet pads are poured
First truss is placed on beams
Concrete is being pour for the stairs
Stairs are complete
Cabinet pads are complete
Trusses are set in place temporarily
Monday, October 28, 2013
Day #43 - It's Monday! Started patio extension!
Patio extension begins!
Hey!! They are trashing my house :)
From a distance!
Sunday, October 27, 2013
Day # 41 & 42 - It's the weekend...trusses get stained and more clean up!
Trusses are stain and ready to be placed!
Day # 40 - Support Beams are up and trusses are built!
The beams are up!!
Trusses are built!
Friday, October 25, 2013
Day # 39 - Busy day!!!
Another productive day!
It's starting to come together :)
The remaining block was placed today!
Trusses are built!
BPG crews having to dig some more!
Wednesday, October 23, 2013
Day #38 - Had inspection on Ramada and filled cells in block with concrete
Day #37 - No visual production...rebar placed in Ramada and ready for inspection
Monday, October 21, 2013
Day # 36 - Block is up!!!!!!
One more block to go!!
Done with the block!
Day # 34 & 35 - Weekend!!!! Just me doing clean up and back-filling :)
Day # 33 - Ramada & Slide/Ramada is ready for another city inspection
The block is ready for it's first inspection!
Coming along.....
Slide/Grotto is ready for inspection!
Thursday, October 17, 2013
Day #32 - Production is picking up again!
BPG Crews having to dig footings
These guys are artists!
The block has begun!!!
Production is picking up again!
Day #31 - Water feature got started
Water feature begins!
Tuesday, October 15, 2013
Day #30 - Production starts back up. Rebar was placed for the Ramada
The Ramada finally begins!
Day #27, 28 & 29.....Minimal production. Installed the drains for the Ramada
Friday, October 11, 2013
Day #26 - Happy Friday! No production today, enjoy the weekend!
Completed work from yesterday!
Thursday, October 10, 2013
Day #25 - Shotcrete today!!!!
Shotcrete begins!
During the process
During the process
Complete!
Wednesday, October 9, 2013
Day #24 - Everything complete and ready for shotcrete (concrete) tomorrow.
Water slide/grotto pad complete!
Spa water feature pad ready!
Spa water feature pad ready!
Ready for shotcrete/concrete tomorrow!
Tuesday, October 8, 2013
Day #23 - Prepped the pad area for the water slide
Prepped the pad area for the water slide & grotto
Day #22 - Continued working on the weekend! Dug and poured the second footer for the raised planter
Footers completed for the raised planters
Day #21 - Working on the weekend! Dug one and poured one footer for the raised planter
Started my raised planters!
Friday, October 4, 2013
Day #20 - First city inspection today.....IT PASSED!!!!!! Whoop whoop, it's the weekend!!!!
Day # 19 - Electrical then pool inspection
All plumbing and electrical complete!
All plumbing and electrical complete!
All plumbing and electrical complete!
Wednesday, October 2, 2013
Day #18 - Plumbers come back to continue
How do they keep track of all these pipes??? And they still need to add more?!
The dogs enjoying the mid day progress...tiring!!!
So many pipes!!
Plumbing at the end of Day #18
Newer Posts
Older Posts
Home
Subscribe to:
Posts (Atom)